good morning to every one
i want standard report t-code for batch expiry ,, and while creating sales order should should check the expiry date of the material , if material batch is going to expire for next 3 months then system shoul don accept that , can any one give me the solution , waitng for reply
solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rahul
Check with LX47, ther u will find total information abt the material when they are going to be expired in batch wise..
Rewards, if it is useful
Regards
Durga Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello, friend.
actually, you can specify remaining shelf life for the material and batches in the material master. you can specify, for example, if the remaining shelf life is less than 3 months, then this batch should not be included in the batch determination.
there are many existing threads on this issue. hope these will help you.
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello, friend.
use MB5M.
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.