on 02-14-2008 2:44 PM
Hi,
I designed a BPM with a sender requesting for a Transport Acknowledgement.
But earlier I defined via IDX_NOALE, that no Ack. should be sent.
My problem is now, that I have a lot of messages waiting for the event 'SEND_OK_TRANSPORT' of object type CL_SWF_XI_MESSAGE.
How can I stop these workitems (>10000 workitems
Is there a report to fix this problem?
Thanks a lot
Regards
Wolfgang
Hi Wolfgang,
If you go to SXMB_MONI_BPE you can see various options to play around with work item and work flows.
if you want to change workflow state manually just execute Diagnosis Processes with Error option here you can edit work item and workflow states.
Cheers,
Jag
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have u tried swwl. I havent heard of any such report to achieve this.
Regards,
Prateek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.