Hi PS expert,
Which one in PS config (SPRO) to configure settlement rule to FXA (fixed asset) or CTR (cost center) ?
Please advice.
Thank you.
Nies
It's difficult to explain the configuration in a single post.
Basic Configuration node for settlement to work in project systems are below:
Project System>Costs>Automatic and Periodic Allocations>Settlement>Settlement Profile
1. Create Allocation Structure (Source cost elements/groups are assiged to settlement cost elements -by cost element or by settlement cost element to receiver categories like., FXA,CTR)
2. Create Settlement Profile (Valid receivers like FXA,CTR and allocation structure etc., are mentioned here)
Also
3. Create Source Structure
4. Define PA Transfer Structures
You the refer the settlement profile in the project profile and maintain the settlement rules on the WBS.
For more information on settlement refer below link on help portal
http://help.sap.com/saphelp_erp60_sp/helpdata/en/6b/566b34b650f777e10000009b38f83b/frameset.htm
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ;
u need to create settlemnt profile to configure settelemnt on AUC or on Cost Ctr.
SPRO >> Project System >> Costs >> Automatic and peridic allocations >> Settlement >> Settlement profile >> Create settlement profile.
Her u can define valid recievers for settlemnt.
If any more help needed do contact .
If found helpfull reward points and close topic.
Thanx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.