hi everybody,

can somebody explain the relevancy of working time in shipping point

thanks

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

pl check this link :

[transportation scheduling|http://help.sap.com/saphelp_46c/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/content.htm]

regards

Manoj_Mahajan78
Active Contributor
0 Kudos

Hello!

Working time from sales view:-

Work times of the workdays defined in the factory calendar.

Use

If work times are defined, lead times can be set in hours/minutes and applied to the work times.

The following priorities are used for scheduling:

Factory calendar and work times maintained

The lead times are used in hours / minutes work time. Here, both the work days defined in the calendar as well as the work times on the individual weekdays (Monday through Sunday) are taken into consideration.

Additionally maintained lead times in calendar days are possibly not taken into consideration if the lead times are not maintained in hours/minutes. The work time would then be zero from the schedulung view.

Factory calendar maintained

The work times in calendar days are used and the workdays defined in the calendar are included. From the scheduling view, each day has 24 hours (in contrast to the lead time in hours/minutes where the work times are taken into consideration).

Additionally maintained lead times in hours/minutes are possibly not taken into consideration if the lead times in calendar days are not maintained. The work time would then be zero from the scheduling view.

No factory calendar maintained

As above, the system calculates only using calendar days, and work-free days, such as weekends or public holidays, are not taken into consideration.

Regds

MM

ranjeetrajendra_jain
Active Contributor
0 Kudos

Working time would check if the shipping point is working or not when delivery is created..

Say you create a delivery after 6.00 and try to PGI it won't allow you as it won't be working..

There is also delivery shediling with time to chack if the spoint if free for shipping to be done..

Former Member
0 Kudos

Hi

This is the working hours of shipping point. this will be used in picking and packing time during proposal of delivery time. and the same is used during route determination

Muthu