Dear all.

We are having two seperate companies SEL & SGPL.

In SEL SAP R/3 and SCM is implemented.

In SGPL only SAP R/3 is implemented.

Now we want to implement SCM in SGPL.

The FERT (for examp-Generator) of SGPL is required by SEL as a dependent item for its FERT .

The isuue is Material code in SEL starts with 5000000 and in SGPL starts with 4000000 for the same Item ( for example - Generator).

Please suggest how this issue can be address.

I mean how we can map SGPL into SCM,so that demand for its FERTs peculates from SEL.

Also we need to give provision in demand planning book for entering direct demand of SGPL FERT.

With best regards,

sajit kumar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You may require to come up with the common code...for better picture.

Answers (1)

Answers (1)

wilian_segatto
Contributor
0 Kudos

Closing old thread.