on 02-09-2008 4:05 PM
Hi
When I do MD02 and then MD04 I see for some sales orders the PR and for some sales order i do not see the PR and sales order
at all in MD04. Where do you set this up? Is this a field setting in the schedule line?
Thank you,
Eric van Zundert.
hi,
is it the same material in both sales orders or different. But to see the stock requirements at MD04 you dont have to run MD02. As soon as you save the sales order, the requirements are populated at MD04.
for the material which is not showing up in MD04, check if the item cat + MRP type -
> mapped to some requirement and is appearing in the sales order.
Also check the value for the strategy group which is in the MRP views.
regards
sadhu kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.