on 02-09-2008 2:17 PM
Dear All
I want to settle cost from a wbs element to upper wbs element.
For that I want automatic settlement generation rule. Is it possible? If yes kindly guide.
From network to wbse its working fine.
Thanks in advance.
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sreenivas
Thanks for your valuable reply.
I have one issue when I assiged Settlement profile with Strategy Sequence SAP060 its gives me message " Do not make any changes (SAP entry)" . What sould I have to do?
Kinldy guide.
In Determine Stretagy for Settlement rule I have created stretagy CP and in setting I assigned settlement Profile and Acct Assg Cat. '4' and account assignement element radio button selected. This is just for your information.
Kindly guide.
Thanks in advance
Regards
Sujit
Hi
I am doing Capital Project for that settlement stretagy is following:
1. Settle Nework cost to Respective WBS element.
2. From WBS element to Top level WBS element.
3. From Top level WBS element to AUC
4. From AUC to FXA.
Everything is working fine only issue with "From WBS element to Top level WBS element", which I have to write manually. I want that also automatic.
This just for your information.
Regards
Sujit
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.