on 02-09-2008 2:24 AM
Hi all
I am trying to publish the results of PP/DS planning results to R/3. Specifically the external procurement. What I need to know is can this be sent periodically using change pointers instead of immediately. I have no problems sending immediately.
I have defined external producement in maintain distribution definition and have set /SAPAPO/C4 to collect changes. However when running /SAPAPO/C5 I get back no change pointers for external procurement... only inhouse production??. The PP/DS global parameters is set to create transfer events aswell.
any input would be appreciated
thanks!
Can you check in /sapapo/c2, if you have distribution definition indeed setup for publication type External Procurement (021) ? I am assuming you have active integration model for the P Reqs, POs, Products and locations setup for distribution definition.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes the sapapo/c2 is defined and the distribution definition is set for external procurement... there are also active CIFs... My issue is specific to sending the data periodically through SAPAPO/c5 via change pointers... the data moves fine immediately to R/3 if sapapo/c4 is set to "do not collect changes"
any further input would be great
thanks!
I meant the transaction /n/sapapo/ccr in APO that compares transaction data between APO and R/3 systems. This is a standard frequently used transaction to ensure that the two systems are in sync. It is in this transaction that I had asked you to check for the checbox referred in my earlier note.