ATP in APO

hitaloc1971
Participant
0 Kudos

How do I define in R/3 that availability check is done in APO?

Best Regards

-Italo

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You need to create ATP check interation model in R/3, ATP check will be done in APO for the material which are there in active integration model of ATP check.

You can select the material in the ATP intergation model based on:

Material

Plnt

Matl Type

PlantSpec. Mtl Stat

MRP Ctrlr

MRP Type

ABC Indicator

or material selection based on TVARVC table variable.

Answers (1)

Answers (1)

hitaloc1971
Participant
0 Kudos

Thank you very much

Regards!