on 02-08-2008 8:35 PM
How do I define in R/3 that availability check is done in APO?
Best Regards
-Italo
You need to create ATP check interation model in R/3, ATP check will be done in APO for the material which are there in active integration model of ATP check.
You can select the material in the ATP intergation model based on:
Material
Plnt
Matl Type
PlantSpec. Mtl Stat
MRP Ctrlr
MRP Type
ABC Indicator
or material selection based on TVARVC table variable.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you very much
Regards!
-Italo