Hi,

In Project iam planning to procure material against to one internal activity.

Now while viewing the report through CN41,Material cost is flowing to Activity,but in material column its not showing any cost.

For activity also i planned 10 manhours.Now while viewing the report its very difficult find the material cost and activity cost.

For Example activity hours cost is Rs1000/- and material cost is Rs100/-.

In cn41 report,its like the folllowing:

Activity----


1100

Material----


0000

All graphic profiles and settings are maintained correctly,but cost is not flowing in Material column.

So pls help me in this regard,

Regards,

Prakash.

Reward points for useful Answer.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Project Infosystem (CN41) is basic reports which gives overall details of the project structure. You need to refer cost element reports (S_ALR_87013542 - Actual/Commitment/Total/Plan in CO Area Currency) to get the detail analysis of various costs in projects. As per standard SAP, distinction of cost at activity level won't available in CN41 reports. You may go for for some develepments of the same.

Hope this will help you.

Best Regards,

Rakesh Pradhan