configurable material

Former Member
0 Kudos

Hi

Dear PS Pals

I have got one scenario to implement which needs repeated operations of one common set of business processes to produce final product.Since every time, scale/set of parameters are different,i need to go for configurable material coupled with assembly processing.Can anybody send me set of configuration guidelines /soft material on adwait.deshpande@siemens.com for doing above job and also piece of advice and experience sharing from you pals.Needs urgent help.

Best Regards

Adwait

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

You need to maintain Planning Strategy 85 or 83 for the material the material master (MRP 3) { 85 is “Assembly processing network with project”, 83 is with network, w/o project.

Also you need to maintain Network parameter for sales order (Transaction CN08).

Amruta