Batch scheduler: Unable to process a job

Former Member
0 Kudos

Hi All,

After importing a transport request in our system, we observed the error in the system log.

An error “Batch scheduler: Unable to process a job” is occurring under the user SAPSYS & is giving priority as high.

Also, this is occuring frequently (every half an hour).

Does anybody have any idea why this is occurring & will it cause any problem/concern. Kindly suggest.

Regards,

Vivdha

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Please check if any job is active under user SAPSYS in SM37. Do a big search may be an year back or so.

If yes then check if you need that job to be running and take an action accordingly.

R,

pankaj