cancel
Showing results for 
Search instead for 
Did you mean: 

CIF Freight cost from R/3 to TPVS

Former Member
0 Kudos

Hi experts,

In on-line help of APO, it mentions freight costs can be sync cost between R/3 and APO. I would like to know how to set up this in CIF, as I didn't see any related items shown in CIF.

Here is link of online help. http://help.sap.com/saphelp_apo/helpdata/en/3e/dfaf376ed96c21e10000009b38f8cf/frameset.htm

Regards,

Jessie.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Jessie,

To the best of my knowledge, you can not CIF the transportation costs to APO transportation lane from R/3. APO TP/VS optimizer works on notional costs & the costs that you define in Tr. Lanes do not represent the exact costs. They are used just to select the most cost optimal mode of transport & route.

You normally refer to R/3 costs in Automatic Carrier selections, in which case the system will refer to the pricing conditions maintained in R/3 based on Shipping Point & Transportation Planning point determination.

I refereed to the Help documentation, but I could not trace this functionality out from it.

Hope this answers your question.

Thanks & Regards

Sandeep Patil

Answers (0)