Hi Guys,
How do you carry out PRT scheduling through MRS? I have assigned PRT (material/ equipment) & they come on planning board but how to schdule it so that it goes with the demand(gets reserved with demand?)?
Regards,
Rajiv
Hi ,
I have to work on the below requirement , for that we need to enhanced the below functionality for the MRS worklist
1. Transfer the order operation system + user status from SAP to MRS
2. Add the additional custom fields viz. for location, appointments and street works etc. to MRS worklist and update them from SAP
3. Highlight the worklist items with different colors for the following conditions:
a. Items with high priority
b. Items not with high priority but with an appointment
4. Identify work list items with street works (future requirement for TMA)
Could any tell me how we can do it above functionality. what are the required Inputs we need to fulfill the requirement
Thanks ,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi mike,
plz check the control key of PRT and in this you will find the check box for scheduling , marking this you requirement can be met.
regards
pushpa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.