Hi guru,

I have a cost activity in my project.

How can I confirm it?

I try with CN25 but in the report, the actual costs are not updated.

Thanks in advance

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Cost Activity is only used to plan costs that are not possible by either Internal/External activities.It's not mandatory to confirm the general cost activities.

Ensure you have the Cost check box checked if you wish to include these activities in costing using the control key (T code OPSU).

But if you want to do a confirmation, maintain the control key (T code OPSU) for general cost activities as 'Confirmation possible but not necessary' and Ext. processing field for example as blank ie., 'Internally processed operation. You then enter the confirmation details (like activity type, hours etc)

Regards

Sreenivas

Former Member
0 Kudos

Hi,

thanks a lot for your help