About BOM Transfer

former_member563943
Participant
0 Kudos

hi all

In transferring the BOM ie CN33... i am not able to transfer the BOM coz it is giving the error message as

"Reference field of the selected activities are not unique"

suggest the solution to it...

thanks in advance

Accepted Solutions (0)

Answers (11)

Answers (11)

Former Member
0 Kudos

Hi,

Please see the entries in "Lot size" tab of MRP1 view of the material master. Please see & correct the entries in " Minimum Lot size", "lot size" , fixed lot size" etc.

Muraleedharan.R

former_member563943
Participant
0 Kudos

I am done with that error.....

thanks for the help n suggestions....

Former Member
0 Kudos

Hi,

You mean to say, you are able to see reservation number in the project builder for the component, but not able to see the same in MD04.

Improbable ...

Can you be more specific.

Muraleedharan.R

former_member563943
Participant
0 Kudos

WELL HERE IS THE ERROR WHICH OCCURED IE

in MD04

"for material xyz: 2.0- is less than the limiting value 0.1-"

nw hw to solve this....???

in the traffic lights the ltd value is 0.1-

Former Member
0 Kudos

Hi,

Are you able to see reservation number in networks?

Muraleedharan.R

former_member563943
Participant
0 Kudos

ya ...and procurement indicates X which is for both internal n external procurement....

Former Member
0 Kudos

Hi,

If the BOM has been transferred, the problem could be with:

1.Material master

2.Procurement indicator in the network against materials

3.Status of the activity / WBS. Have they been released.

Further, what type of materials are you using ? Category - L, N ??

Whether the materials are expected to create WBS reservation, network reservation, purchase requisition ..,.?

Most important - Material master -MRP1 tab->MRP type (whether maintained or not

WBS/ Network - Released or not ?

Muraleedharan.R

former_member563943
Participant
0 Kudos

ya WBS n N/w has been released

the type of material is L and its for WBS Reservation...

and i coud not find the procurement indicator in newtwork...'

which is the table for material master....????

Former Member
0 Kudos

Hi Preeti,

Has the BOM been finally transferred. If yes, kindly close that posting and create a fresh thread for the new issue which seems to me not related to BOM transfer.

Regards

Muraleedharan.R

Former Member
0 Kudos

Hi,

Have you been successful ?

You need not do anything in CN38.

Do the other settings recommended.

To ensure that the BOM is Ok, pl check the following :

Go for display of WBS BOM -CS73

Display the BOM.

Select one line item by clicking on the left side of the item sl number->GOTO->ITEM.

Check for reference point.

Is it allright ?

Otherwise, assign reference point to the BOM item.

Muraleedharan.R

former_member563943
Participant
0 Kudos

Ok i will do that.....

thank u

former_member563943
Participant
0 Kudos

i am in need of help again...

Nw i have proceeded with BOM transfer...

i need to go to MD04 n check tht..and then move to MD51 n convrt the planned order into production order which i have done...nw after tht i need to execute tht proj in TCODE ME5J

But the pblem is tht its nt getting executed and its nt even reflecting any error too....

but when i went back to MD04 n choose Goto mat list icon it will give an red traffic light and says tht supply of mat is 2.0- but limitation is 0.1-.....

so i want to know where can i change the this mat supply field....

thanks in advance....

former_member563943
Participant
0 Kudos

i am in need of help again...

Nw i have proceeded with BOM transfer...

i need to go to MD04 n check tht..and then move to MD51 n convrt the planned order into production order which i have done...nw after tht i need to execute tht proj in TCODE ME5J

But the pblem is tht its nt getting executed and its nt even reflecting any error too....

but when i went back to MD04 n choose Goto mat list icon it will give an red traffic light and says tht supply of mat is 2.0- but limitation is 0.1-.....

so i want to know where can i change the this mat supply field....

thanks in advance....

former_member563943
Participant
0 Kudos

but its the continuation of that BOM Materials....i mean the error is still at BOM Materials in TCODE MD04....So i continued the thread

Former Member
0 Kudos

Hi,

Pl ensure the settings suggetsed and try out.

Muraleedharan.R

former_member563943
Participant
0 Kudos

ok...thanks for the info...

former_member563943
Participant
0 Kudos

yes i am as i am beginner and doc is quite confusing...

if u have any valuable mat pls send it my id

Preeti_bharati@datamatics.com

if i dont maintain the logical link such as plant or n/w or wbs then hw will proceed further....i mean if i keep blank in cn38

wat we do in TCODE OPMF????

thnx in advance

Former Member
0 Kudos

Hi Srinivas,

I thought this customization is relevant for earlier releases, i.e releases prior to 4.70. Correct me, if I am wrong.

Regards

Muraleedharan.R

Former Member
0 Kudos

Yes I agree. All I want is to ensure blank entries in those fields.

Regards

Sreenivas

former_member563943
Participant
0 Kudos

Thanks both of u....

ya i have maintained the ref point for Plant....

and hey nw i created the simple proj and transfered the materials without the ref point mentioning in CJ20N... and i have mantioned the ref point for those BOM Items in CS71

is this correct way...

am i doing in correct procedure....

pls let me know...

Former Member
0 Kudos

You seem to be confused. Maintain the reference points both in BOM and Activity but keep the entries blank in SPRO node CN38

Regards

Sreenivas

Former Member
0 Kudos

Hi,

Please ensure that following parameters are maintained in the BOM transfer profile:

Plant

BOM usage

BOM Application

Required quantity (default it as 1)

WBS BOM -(I assume you are using WBS BOM)

Tick the radio button- All items

Further, please check whether you have deleted or set deletion flag for any actvity in the network for which you had assigned the same reference point. If deletion flag has been set for any such activity, reset the deletion flag and remove the reference point assignment from those activities, and set the deletion flag again, if required.

Muraleedharan.R

Former Member
0 Kudos

Hi,

Please check whether every BOM item has reference point.

Muraleedharan.R

former_member563943
Participant
0 Kudos

ya i checked....and gave the reference number still the same error is occuring....

is there any pre-requisites need to be checked

Former Member
0 Kudos

The problem is with the SPRO configuration node 'Define Fields in BOM and Activity as Reference Point' (T Code CN38). Maintain the fields as below or keep them blank:

BOM field name- RFPNT

Network field name-RFPNT

If you have any other field (Plant - WERKS) to be used as reference point you need to mention it here.

Regards

Sreenivas

Former Member
0 Kudos

Hi,

You might have assigned the same reference point to more than one activity. Each activity in a network should have a distinct reference point and this should be entered in the field "reference point" under tab Assignment. The required reference points must have been created in customization.

Regards

Muraleedharan.R

former_member563943
Participant
0 Kudos

Only for one activity i have choosen the reference point ...for other activities the reference field is kept blank