Dear Consultants

We want to deactivate QM for some plants.

Say we have two plants P001, P002.

We maintain quality view for P001 with QM Proc Tick, QM control key and insp types. Here normal qm process will work.

But in other plant P002, we want only QM proc tick and QM control key and NO INSP TYPE. So that stock should not move to Quality after GR. But users are wrongly enter inspection type.

Can we deactivate QM in such a way that even if users have maintained insp type in material master, stock should not move to quality after GR (only for one plant). We tried to do this by authorisation but its not working.

Kindly revert.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can remove the tick of 'Post stock to Quality Inspection' in default values proposed for the inspection type select in SPRO.

Hence, when the user will select the inspection type, the option of posting stock to unrestricted use will not be selected by default. User will have to select it purposly.

Regards,