Hi All,

Can you please tell me - where the BOM Explosion No. is assigned with Plant?

Is there any setting for BOM explosion no. - number range assignment with plant.

Thanks in advance

regards,

snehasish maity

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear snehasish

1. Starting from the MRP menu, choose Master data => BOM explosion number => Edit.

The system displays the initial screen for maintaining the BOM explosion number.

2. Choose .

The screen for maintaining the BOM explosion numbers now appears.

3. Choose New entries.

A screen now appears where you can enter new BOM explosion numbers.

4. Enter data as required.

o BOM explosion number

The BOM explosion number is the object for which the following data is maintained. It can be entered alphanumerically.

o Fixed key date

The fixed key date determines which bill of material is exploded.

o Plant

You can also specify a BOM explosion number for a specific plant. Enter the appropriate plant in this case.

o Material

You can specify a BOM explosion number for a specific material. Enter the appropriate material in this case.

o Status

You can set the BOM explosion number to active or inactive using the status field. Only active BOM explosion numbers are used in the planning run.

5 Save your entries.

Thanks

G. Lakshmipathi

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi.....

pls can anybody pls explain end 2 end bom configaration.

each and every setting in bom.

Aditya