Dear SAP Guru's
This is regarding the Posting goods issue from SALES ORDER
SCENERIO.
1. Posting period open :
2007/10 & 2007/09
As posting in Material Management allows only on previous month and current month.
When a back dated order is created the PGI is not happening.
Also in the schedule line level the BOM
1. The BOM header material gets the schedule line as the back date when set
2. But the child parts of the material gets the schedule line of the todays days not of the back date.
Please suggest if the PGI would be possible backdated my scenerio.
regards,
Amlan Sarkar
hi
Close the posting periods using t.code MMPV one by one from 2007/10 to the current month.
baburao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
Use the T-code MMPV or MMRV for closing the periods and check in the log for the correct period of posting.
regards
VK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.