Dear QM masters,

I have following scenario:

Material A has Material B as a component and Material B has Material C as component. Material A is batch managed. Material C has in-process inspection with partial lot using inspection point functionality. Last result recorded for this in-process inspection should be used for quality certificate of Material A.

Thanks a lot in advance for any help extended and will be rewarded with maximum points.

Thanks and regards,

Devang

Accepted Solutions (1)

Accepted Solutions (1)

former_member42744
Active Contributor
0 Kudos

Since you are in ECC 6.0 you can also use batch derivation to have the components values copied to the next material being made. In this way, batch values for Material C get copied to material B batch and material B batch values get copied to Material A batch.

Then on the cert, you only need to report the value from the material A batch. No need to set up the result from production chain in the COA profile.

Craig

Answers (1)

Answers (1)

Former Member
0 Kudos

you are in which SAPm version? 4.7 or lower?

former_member263130
Participant
0 Kudos

Dear Rajesha,

We have SAP-ECC 6.0.

Thanksand regards,

Devang

Former Member
0 Kudos

Dear,

Then it cerificate profile, you mention the required char in the certificate and enter the Results origin as Inspection/batch from the production chain

it will work for you