Dear friends,
I have defined a XI track in NWDI/CMS. But on Assembly tab I get a conflict error. The log message is:
Info:Starting Step Check-assembly at 2008-01-21 17:42:04.0367 +0:00
Info:Checks for software component A_TEST are performed now:
Info:Checks for software component A_TEST finished succesfully
Info:Checks for software component I_FGT are performed now:
Info:Checks for software component I_HGFfinished succesfully
Info:Checks for software component HGF are performed now:
Info:Checks for software component A_HGF finished succesfully
Info:Checks for software component O2C are performed now:
Info:7XI conflicts
Info:Step Check-assembly ended with result 'error' ,stopping execution at 2008-01-21 17:42:07.0394 +0:00
Can you help where to look and what to do?
Kind regards,
Kamran
Hi,
As you know Assembly tab is used after import in the consolidation system, this is where you assemble transports of software component versions.
Please go through the attached refereance document.
It will help to verify with you configuration to creaet XI track
http://help.sap.com/saphelp_nw04/helpdata/en/a6/a4214174abef23e10000000a155106/frameset.htm
http://help.sap.com/saphelp_nw04s/helpdata/en/e9/c7cb6545a3446b92eff4f9ba876072/frameset.htm
http://help.sap.com/saphelp_nw04s/helpdata/en/e9/c7cb6545a3446b92eff4f9ba876072/frameset.htm
http://help.sap.com/saphelp_nw04/helpdata/en/a6/a4214174abef23e10000000a155106/frameset.htm
Thanks
Swarup
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The following logs exist for the assembly step:
● Check-assembly: Checks whether the prerequisites for a successful assembly exist. The following individual checks are performed:
○ Are there open build requests in the buildspace?
○ Are there open conflicts in the workspace?
○ Are there any broken DCs in the build compartment?
○ Are there any dirty DCs in the build compartment?
○ Are there any problem DCs in the build compartment?
○ Are there any pending activities that are not yet completely activated?
For detailed monitoring of a central build, use the Web UI of the Component Build Service (CBS).
http://help.sap.com/saphelp_nw04s/helpdata/en/ab/40833c87ac4d0cb5c4c44da8259386/frameset.htm
If the track deletion in CMS should fail for some reason, CBS administrators can delete a buildspace manually.
...
1. Start the CBS Web UI.
2. Navigate to the Buildspaces view.
3. Select a buildspace to delete.
4. Choose Delete.
Let me know if this could help you
thanks
Swarup
Swarup,
I can't see any XI buildspaces in CBS. And other buildspaces are clean.
But I can see a conflict tab in integration repository of our Consolidation system with the same SWC name as described in the log of the assembly step.
If I delete the objects in the conflict tab they return as soon as I want assemble some other imports.
Kamran