Hi experts,

I’m currently using Change Request Management scenario in SAP Solution Manager for implementing a solution, and i’m facing a problem with the way the imports are done with SolMan : i have to perform some manual steps in the middle of a version import, how can i possibly do that while Solman will import all the transport request from the import queue at one time ?

What would you advise in such a situation ?

I’m at your disposal for any additional information.

Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

That is one of the items on my enhancement list:-). The only way to accomplish that is to use a combination of Normal and Urgent corrections or just several Urgents. That is the only way to allow a manual step between transports.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi, Please Go to SAP Note: 1046219 may resolve your problem.