Hi all,

we have a sales order of 100 qunatity. but my client don,t want to be delivery them at a time. he wants to be delivered the goods 25% of that stock for three months and accoring to that ratio he want to delivery the goods for the next months.

please give me a light on this. is it possible in sap. if it is possible please tell me the way

IT IS VERY URGENT

REGARDS

satish

thanks in advance

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member204513
Active Contributor
0 Kudos

Hi Satish,

The delivery % is linked with stock of the material am I correct,

or

Your client want's to supply 25% of goods to the customer in three continues months.

You have to go for new enhance ment or using User Exit with the help of ABAPer with the logic between stock of the material and scheduleline corfomation date and quantity for that customer ,then the dilivery will be created based on the schedule lines of the sales order.

Thanks,

Murali.

chaitanya_deodhar
Participant
0 Kudos

Please try to berek up the scedule line quantity according to the dates.

Former Member
0 Kudos

HI

satish,

Scheduling aggrements is well suited for this business scenario. For this document type is "DS" and item category is "LPN" .

if it helps reward me.

regrds,

kishore.

Former Member
0 Kudos

Hi kishore

could u please tell me how to done by step by step process

thank in advance

regards

satish

Former Member
0 Kudos

http://web.mit.edu/sapr3/windocs/bpors11m.htm

http://help.sap.com/saphelp_470/helpdata/en/78/2085347860ea35e10000009b38f83b/frameset.htm

http://help.sap.com/saphelp_46c/helpdata/en/d6/d77f381b2f3216e10000009b38f842/frameset.htm

http://help.sap.com/saphelp_46c/helpdata/en/93/7439fb546011d1a7020000e829fd11/frameset.htm

check these links, iwll send u the config settings.

.

These are the steps u hav to be followed

VA31-SCh Agreement(in delivery due lines split the quantity into ur ratio with future delivery dates)

VA01-Sale order

Vl01n

VF01

reward me if it helps