Hi experts,

How is an standard price of a material determined.

I learnt that its been done from the purchase order value.

But i appreciate if any one can tell me the calcualtion process and logic behind it.

Setting step too !

thanks and regards

Monti

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear monti

Check the link

[Updating the Standard Prices |http://help.sap.com/saphelp_46c/helpdata/en/7e/cb885543a311d189ee0000e81ddfac/frameset.htm]

Thanks

G. Lakshmipathi

Answers (3)

Answers (3)

maheshbabu_mg
Advisor
Advisor
0 Kudos

Hi,

While taking a standard costing run ( Standard cost for the Product) system will refer the Activity ( Via routing & costcentre) Material prices ( via BOM & material master) and ofcourse the Overheads.

This is basically the standard price...Means the price if the material is produced as per the planned prices & rates.

Anyhow this is a basic overview... Procedures may change on business needs

Thanks & regards

Mahesh

Former Member
0 Kudos

Hi,

please check this on Standard price calculation.

Link: [http://help.sap.com/saphelp_470/helpdata/en/90/ba6cc7446711d189420000e829fbbd/content.htm]

regards

Sadhu Kishore