our company is using Finance and PS. Now we want to implement
logistics. for that we need to activate the option Valuated Stock. How
can we do the for existing project definition and wbs element.
Regards
Ganesh
Hi,
For existing projects, which are maintained with 'No project stock/Non-valuated stock' u can't change to 'Valuated stock'.
When you create a new project, initially u can chose whether to manage with valuated stock or No stock/non valuated stock. Once u save the project, u can't make any changes
Thanks
Kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As fas as I know, change over to "valuated stock' is not possible for existing projects. Even if you change Project defition to "Valuated stock", the same will not be inherited by WBS elements.
Regards
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.