Change Valuated Stock option in Project Defintion.

Former Member
0 Kudos

Hi

our company is using Finance and PS. Now we want to implement

logistics. for that we need to activate the option Valuated Stock. How

can we do the for existing project definition and wbs element.

Regards

Ganesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

For existing projects, which are maintained with 'No project stock/Non-valuated stock' u can't change to 'Valuated stock'.

When you create a new project, initially u can chose whether to manage with valuated stock or No stock/non valuated stock. Once u save the project, u can't make any changes

Thanks

Kishore

Former Member
0 Kudos

Hi,

As fas as I know, change over to "valuated stock' is not possible for existing projects. Even if you change Project defition to "Valuated stock", the same will not be inherited by WBS elements.

Regards