Start date in SNP Planned Order

Former Member
0 Kudos

Hello,

We are running SNP Heuristics. It creates SNP Planned Orders and send it to R/3.

R/3 does backwards scheduling and puts the start date on the order .

When the new order gets to APO, it still doesn't change the start date on the SNP Planned Order.

Is there any way to get the new date from R/3 to be in APO ?.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

OSS 423626: Different dates in R/3 and APO: (for orders sent from R/3 to APO)