on 01-29-2008 8:56 AM
Dear all
We are running batch job for autamatic invoice after Post goods issue..
It was working till y'day and suddenly it is not getting executed .It shows a huge delay..
Batch job program was SDBILLDL
Can u please tell us what could be problem for delay in batch job execution...
Batch job status is released...But not getting executed every 15mts
How to find out which has caused delay...for batch job running...
Regards
Sudha
There can be two reasons.
1. If the data or the number of documents being processed is huge.
2. If there is an error or wrong data being picked up in any one of the document can lead to batch job being slow.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey,
Check your settings for the start time is it immediately or after some time if the time is set to as 15 mins after release then it will give you a clear picture of it and take help of basis team to work on this issue !!!!
Regards
Rohit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do you have enough background processor to execute the batch job, when there is no processor free then it will be delayed, you may use ST13 , BATCH_JOB_ANALYSIS and which will give you fair idea.
Regards,
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.