want to know something about SLD transport,

1. If i transport a TS from one SLD to another, will it also automatically transport all products and software components refered by this TS,

2. If the products and Software component refered by this TS, are already present in the second SLD, will it update the software components,

3. If i transport a software component, that is already present in the other SLD, will it update it (overwrite it),

pls help

Accepted Solutions (0)

Answers (2)

Answers (2)

prateek
Active Contributor
0 Kudos

1. If i transport a TS from one SLD to another, will it also automatically transport all products and software components refered by this TS,

No. U have to transport it separately

2. If the products and Software component refered by this TS, are already present in the second SLD, will it update the software components,

Yes

3. If i transport a software component, that is already present in the other SLD, will it update it (overwrite it),

Yes

Regards,

Prateek

Former Member
0 Kudos

thanks prateek and swarup,

i tried them...ur answers helped me......

Former Member
0 Kudos

Hi,

1. If i transport a TS from one SLD to another, will it also automatically transport all products and software components refered by this TS,

-


>

Irrespective of whether you have a Common SLD or Different SLD's , you need not create the SWCV manually in your SLD. When you transport the SWCV and import it into your new IR, the corresponding entries will happen in SLD.

In CMS transport, you could select the individual object or namesapce or all software component to be transported.

refer below links for CMS

CMS for SAP Exchange Infrastructure

https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/b8d8f7b2-0701-0010-b09a-cda4cca2...

Configuration of CMS in Central NWDI & SLD to transport XI objects

/people/praveen.mayalur/blog/2007/05/31/configuration-of-cms-in-central-nwdi-sld-to-transport-xi-objects

How to Use CMS in XI 3.0.pdf

https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/43f5d790-0201-0010-2984-ff72d822...

CMS based transport in XI

https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/b8d8f7b2-0701-0010-b09a-cda4cca2...

https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/9e76e511-0d01-0010-5c9d-9f768d64...

In your source system,. say tool--> Export --> using file system and then select your SWCV. The exported TPZ file wll be placed in the EXPORT directory of your server.

Now, copy this TPZ file into the import directory of your new server and then tolls --> import.

For the export and import directories, XI Homepage --> Administration --> General Information.,

2. If the products and Software component refered by this TS, are already present in the second SLD,

will it update the software components

---> Hi yes it will update the existing Software component refered by TS. No need to create another one.

While transporting the modified object

Refer CMS links mentioned above. Here you could select the individual object or namesapce or all software component to be transported.

3. If i transport a software component, that is already present in the other SLD, will it update it

(overwrite it),

--> It depends upon the object you are transporting. For e.g if you have transported the whole software component then the existing will be overwrite. Or if you add individual object or namspace then only that part will be overwritten.

Here you have option in CMS transport to mentioned, if you wish to delete any object, then jsut delete it from development SDL i.r. IR or ID and transport deleted object to Qu. you will get that option in CMS.

Thanks