on 01-28-2008 10:55 AM
when creating a material in the transaction code MM01 there is a field called MRP profile
where do we define it and what is the purpose of it
REgards,
Murali
got the answer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
MRP - Material Requirement Planning
It is uesd to determine the SCHEDULE LINE.
SCHEDULE LINE = ITEM CATEGORY + MRP TYPE
Materials Requirement Planning (MRP) is a scheduling procedure for production processes that have several levels of production. Given information describing the production requirements of the several finished goods of the system, the structure of the production system, the current inventories for each operation and the lot sizing procedure for each operation, MRP determines a schedule for the operations and raw material purchases.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.