when creating a material in the transaction code MM01 there is a field called MRP profile

where do we define it and what is the purpose of it

REgards,

Murali

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

got the answer

Former Member
0 Kudos

MRP - Material Requirement Planning

It is uesd to determine the SCHEDULE LINE.

SCHEDULE LINE = ITEM CATEGORY + MRP TYPE

Materials Requirement Planning (MRP) is a scheduling procedure for production processes that have several levels of production. Given information describing the production requirements of the several finished goods of the system, the structure of the production system, the current inventories for each operation and the lot sizing procedure for each operation, MRP determines a schedule for the operations and raw material purchases.