Hi
How the cProjects is pulling/pushing data from SAP ECC Modules(HCM,MM,SD,etc) ?
Will it be interacting directly with the database of SAP ECC ?
What will be the mechanism used Bapi/IDoc ?
Case1 : cProjects is installed along with Ecc 6.0
Case2 : cProjects is a standalone installation
How to handle large data transfers eg: b/w HCM and cProjects ?
Pls give ur thoughts.
Thx & rgds,
Tom
Dear Tom,
Please use transaction DPR_FIN_GECCO_R3_CUS to communicate with your target ERP component for controlling.
For pushing data from HCM to cProjects, you can use the report PFAL (if cProjects is on a different system), or make settings in transaction OO_CENTRAL_PERSON for integration of Business Partners with HCM Master data (if cProjects is within the same system).
Let me know if this helps.
Regards,
Vivek Pandey
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
12 | |
7 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.