Adding some more line items in the unconfirmed Transfer Order

Former Member
0 Kudos

Hi All,

We do kitting activity at our warehouse i.e. several components make up an assembly of a particular final product. The WH creates a production order(BOM) based on which the system creates TO wherever stock of individual components are available for picking. However, the remaining components which are required to make up the product are still awaited in such a case (stock unavailable at present). Under this situation, is it possible that the balance remaining components can be added to the same original TO created earlier (i.e. where only available line items of that TO is confirmed and the TO header is still open).

Alternatively, can we add some more line items in the same unconfirmed Transfer Order to facilitate this kitting process and thereby confirming the TO header finally.

A quick feedback will be appreciated. Thanks.

Regards

Jaman

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

.

Former Member
0 Kudos

Hi,

If you know what all the items you will include in one TO, even though you haven't pick the items;

In the TO, you have an option to make the items "Inactive" for which picking hasn't been done.

After making the items "Inactive", if you save the TO, it will allow you to confirm the TO, but then, it will create the new TO with the inactive items.

Hope its clear.

Aktar

Former Member
0 Kudos

Standard SAP does not alow to add line items in a TO pending for confirmation.

Make a seperate TO for more items and confirm it.

OR

Consult with the development team to make a customized transaction to cater the requirement