Dear All,
Any one could teach me how to make validation in WBS for company code. For example, in basic data tab i put company code FNW, then i put different company code in assignment tab : as a result system will prompt error message. In other words, company code in basic data tab and assignment tab must be same.
Please advice.
Nies
Hi,
In my earlier posting, the text got a little bit distorted. For clarity I will bring out as below:
Once you use the substitution push button, in the new window, use the + sign push button. There you select PRPS-ABUKR as the field to be substituted. In the next window that opens, you have the following options: Constant,Exit,Field -Field Assignment. Select "Field-Field Assignment". Now the new "field is substituted by" field appears.Click the radio button and select PRPS-PBUKR and save the substitution
Now assign the substitution to project profile.
Regards
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Go to OPSA-Project Profile and maintain this substitution in the control tab in the field WBS elements. Better check the Auto substitution as this helps in automatically calling the substitution when you try to save the project.
Regards
Sreenivas
This was already mentioned in earlier posts. Please read the replies carefully!
Closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Assigning project profile ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The substitution shall be as below:
Field is substituted by
Req,Co.Code PRPS-PBUKR
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Sreenivas is definitely right if the case is as he described. That is, if the user enters a requesting cost centre which doesn't belong to the company code substituted.
If that is not the actual scenario, one can go ahead with substitution for which Sreenivas has already given basic steps.
Nies has to take a call assessing the practical situation.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nies,
This is a fit case or substitution. With substitution, you enter the company code only once (may be in basic tab), and the assignment field is substituted with this company code.
If you have any further logic to determine the company code, you can even default that value in both the field also using substitution.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Murali
I too thought so but the problem with substitution here is:
If the user enters Requesting cost centre (which belongs to a different company code) system will try to default this into Requesting company code associated with this Cost Centre first. And while saving the WBS it might again give an error saying that the Requesting Cost Centre is not available in the substituted company code.
Hope I'm right!
Regards
Sreenivas
I would still recommend Validation but let us wait for view's from Muraleedharan.
Substituion can be built as mentioned below
T Code OPSN
Choose WBS Element
Create new Substitution
Create new step
Mention the prerequisite (PRPS-ABUKR equal ' ' i.e., Blank)
Mention the Substitution (PRPS-PBUKR)
Save
Go to OPSA-Project Profile and maintain this substitution in the control tab in the field WBS elements. Better check the Auto substitution as this helps in automatically calling the substitution when you try to save the project.
Regards
Sreenivas
Pls close the post if satisfied.
If you don't have the scenario of Requesting Company Codes (used in conjunction with IM) where you try to create an asset for another company code, just hide the fields (requesting cost centre and requesting company code using field selection T code OPUK) so that no user meddles with it.
Validation can be built as mentioned below
T Code OPSI
Choose WBS Element
Create new validation
Create new step
Mention the prerequisite (PRPS-ABUKR not equal ' ' i.e., Blank)
Mention the check (PRPS-ABUKR not equal PRPS-PBUKR)
Mention the message with field message type as 'E'
Save
Go to OPSA-Project Profile and maintain this validation in the control tab in the field WBS elements. Better check the Auto Validation as this helps in automatically calling the validation when you try to save the project.
Regards
Sreenivas
Pls close the post if satisfied.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.