I am facing problem while assigning multiple staffing to project role.

In the project role, we are doing staffing ( assigning BP). While assigning the BP's getting below errors.

-


Resource assignments overlap

Message no. DPR_BUPA_LINK004

Diagnosis

The validity period '10.02.2008'-'01.03.2008' for the assignment of project role Product Manager and ' Rakesh Pradhan' overlaps with the validity period of the assignment ''.

However, the project role type does not allow several staffings to be edited at the same time in the project role.

System Response

The system does not allow this constellation of data when saving.

Procedure

Check and correct the start and finish dates of the staffings affected.

-


Request you to advise in fiixng the issue.

Thank you for your cooperation.

Regards,

Ranjan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Biplab,

For multiple staffings in the same time frame, check the option of 'Edit in Parallel' in the Role Type settings in SPRO.

Let me know if that helps.

Regards,

Vivek Pandey

Former Member
0 Kudos

Hi Vivek,

Thanks a lot for your suggestion. My issue got solved.

Regards,

Ranjan