Hi experts,
I would like to know where I can set a delivery lead time. In my current system, nothing can be confirmed unless I have set the delivery date to 3 working days after system date(I have enough unrestricted use stock). I wonder is there a parameter/configuration that make the system to have such behaviour. Thanks in advance.
hello, friend.
some of the places you can look are: the material master (mrp views) and the shipping point (processing times).
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
run MM03 and check MRP1 - Scheduling "Plan del time" and MRP2 Av.check "Total rep. lead time"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.