Hi,
If you are doing system upgrade for DEV and QA from 4.6c to ECC 6.0, is it still necessary to have a client refresh from PRD to QA?
If yes, which would be better to do first? upgrade or refresh?
Thanks
If you decided it is needed, you will have to do the refresh before the upgrade since you need the same level of SP's for each system.
Should you do a refresh? I would since testing on QAS is supposed to be a dry run for testing a production system.
Hope that helps.
J. Haynes
Denver, CO
Edited by: Joe Haynes on Jan 24, 2008 2:16 PM