Transporting projects from Dev. system to Prod. system

Former Member
0 Kudos

We have created a number of projects in our development system and now want to move a few of the project to our production system.

Is there a way to transport these projects to the production system

Regards

Don

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Don,

have you tried transaction SOLAR_PROJECT_ADMIN ??

There you can select the project and click on the truck to transport it.

Thomas

Answers (2)

Answers (2)

Former Member
0 Kudos

Good Day......

I have used "the truck" and everything seemed to work ok. Transport was created and we migrated the transport to the production Solution Manager system.

When I tried to open the project in Project Admin/Solar01 I got the following message.

"The specified structure does not exist"

Any thoughts........

As well, is there a way to include all of the project documentation within the transport.

Regards

Don

Former Member
0 Kudos

Hello,

Please make sure that the customizing is set up accordingly in the target system. Also check SAP Note 1134578 and see if this resolves this issue.

Regards,

Thomas

Former Member
0 Kudos

Thanks Thomas, I will look at the customization of our Prod. system and review the SAP note

Thanks Again,

Regards

Don

Former Member
0 Kudos

Thanks Thomas. I think I will try that.

Man, do I feel like I asked a dumb question of the day! In my own defence, I did see the "truck" but working mostly in release management, I thought the truck was for releasing not creating.

Thanks again Thomas

Regards

Don