Order type Z031 plant AT01. No checking rule mantained for operation

Former Member
0 Kudos

Hello PS Gurus,

I am trying to create a new element PEP, and when i tried to release the element PEP i get.

Order type Z031 plant AT01. No checking rule mantained for operation

Can someone tell me what is missing in our customization?

Best Regards

João Fernandes

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Can you eloborate your question ?

What is this new element PEP? WBS,Order???

Where (using what transaction) are you creating this element?

Regards

Sreenivas

Former Member
0 Kudos

Hello Sreenivas,

Thanl you for your answer.

I am using transaction CJ20N and i am trying to create a WBS element.

Best Regards

João Fernandes

Former Member
0 Kudos

I assume you are trying to attach materials to network activity which is assigned to WBS.

Your error is because of missing configuration in below mentioned node:

In SPRO maintain the 'Define Checking Control' under Project Systems->Material->Availability Check (T code OPJK)

For plant AT01 and Order Type Z031 maintain parameters which are suitable to you. Before this you need to check the node OPJJ.

Regards

Sreenivas

Pls close this post if satisfied.