on 01-23-2008 4:33 AM
Hi,
Is it possible to disable the budget check at the WBS element ? I tried to change the system status, but unfortunately, I cannot amened the System Status.
Does this budget check has a user exit ? If yes, I would like to know what is the name of this user exit, just in case it cannot be controlled at the WBS element Master Data.
Regards,
Leslie
Hi Leslie,
The T.Code for deactivation is CJBW.
Other solution is that, in budget profile, the field Activation type can be left blank.
regards
Pratap.V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pratap,
Thanks.. This should solve the problem. I cannot do it at the budget profile level as the same
project is also used for other projects, whereby budget check is needed.
Points have been allocated to you..
Cheers...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
If your query is to supress the budget availabilty check, then you can do it by using t code CJBN, this will deactivate the availability control and then run CJEN which will update the database.
Regards,
Hemant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.