on 01-22-2008 9:06 AM
dear ps experts,
wud like to know in any report of S_ALR*
to know the budget updates in a project
1. first cj30 & cj32
2, later after some time cj36 & cj32
wud like to know which report shows that cj30 & cj32 history
and when cj36 & cj32 history.
because every update at cj30,cj32,cj36,cj37,cj34 there is document created in sap, how to view these details as &when required
thanx in advance
regards
srihari
ps : s_alr_87013560 is of now use for my requirement
Hi Ediga,
A document number gets generated whenever you make any Supplement or Return or Transfer.
Go to the T.Code CJ3B and enter the document number. You can see the updates made.
Hope this solves your issue.
regards
Pratap.V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
When you go into CJ3B, it asks you for the document number. Then press F4, this will take you to another screen. Here you have a facility of entering the WBS element. Enter the Top Level WBSE of the project for which you want to see the detail. Then it will show the list of documents generated for that project.
Hope this solves your issue.
regards
Pratap.V