Hi All
I need to create a BOM that contains different materials depending of what date it is. I.e. the BOM changes from a specific date. Does anyone know how this is set up?
/ Henrik
hi,
are you referring to a sales BOM or production BOM. However in case a sales BOM while creating the BOM maintian the required components into it with the required validity dates. So when you create a sales order automatically those components which match the specified date criteria are exploded and not the ones which are out of validity.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Henrik,
If you want MRP to explode your BOMs according to date you can define this:
SAP menu > Logistics > Production > MRP > BOM by Date (OPPP)
http://help.sap.com/saphelp_46c/helpdata/en/f4/7d2aea44af11d182b40000e829fbfe/frameset.htm
BR
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.