I am doing Purchase Order against project for service,assigning WBS Element in it,
and doing service entry sheet against that P.O.
But I am not getting plan & actual cost reflected in Project builder & reports.
Is there any setting for getting Plan & Actual cost ?
Have you accepted the service entry done? Actual Costs wouldn't appear unless you accept the service entry.
If you haven't done planning (T Codes CJR2 or CJ40), Plan costs wouldn't appear on the WBS.
You should be able to see commitments on the reports if you have the configuration settings for commitments.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pravin,
Check if any Costing variant is maintained in your Planning Profile through OPSB.
1) If no, then maintain it.
2) if yes, then check whether any strategy is maintained for plan and actual cost derivation through OKKT.
regards
Pratap.V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.