on 01-18-2008 5:19 AM
Hi there,
Can we have a control so that if the Quality certificate is not received from the vendor then the GR will not take place or the payement will be blocked ...
Please tell me on the same...
Thanks & Regards
Kaushik Choudhury
hi
yes you can do this provided you have made the customized settings for certificate type .
while customization of the certificate type there are various options you can provide
Type of control used by the system if the certificate required at goods receipt is not provided. The deciding factor is whether or not an inspection lot is created at goods receipt.
The system allows for the following cases:
With lot: Status in inspection lot Without lot: Blocked stock
With lot: Status in inspection lot Without lot: Error message
With lot: Error message Without lot: Blocked stock
With lot: Error message Without lot: Error message
With lot: Status, no skip-to-stock Without lot: Blocked stock
With lot: Status, no skip-to-stock Without lot: Error message
Warning
Information
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thyagarajan,
If the inspection type 01 is active for the matrial then the lot will be created with GR. Am I correct ??
How can we control that the GR will not be done if the certificate is nor received...
Can you please explain in detail
With lot: Status in inspection lot Without lot: Blocked stock
Is that means that if the lot is created then the GR will be done or else block the stock & no GR will be done ....
Please explain me ...
Thanks & Regards
Kaushik
If you activated QM in procurement and certifcate recipt is a must in Define Control Keys and Define Keys for Certificate Processing, then system will prapose a field to enter whether yoiu received the certificate or not.
If the certificate is not received and you entered No during GR, then the inspection will be updated with "certificate not received" and you cannot proceed furthur.
Once you receive the certifcate you can up date the status in QC52, which will update the status in quality inspection that certificate received so that it will allow furthur porcess.
i hope you are clear
Hi Kaushik,
We have the control for quality certificate.For That, if we make setting in Material master QM view for Certificate, then on recieve the material MIGO ,system ask If Certificate enclosed ? Yes or No,
So on MIGO we have control , if certificate not enclosed.
Regards,
Neeraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.