Hi All,

In CN41 we have values for actual & planned work as well as actual & planned cost. My requiremnet is to see the POC of these values in CN41. For instance

POC Work = (actual work / planned work)*100

POC Cost = (actual cost / planned cost)*100

Kindly advice how i can get this.

Thanks & Reagrds

Sreekanth

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I doubt whether it is possible. Why don't you use reports like S_ALR_87013532 which gives planned, Actual & Variance ?

Muraleedharan.R

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Are you looking for something apart from "Processing Pecentage of Work" which is already available in CN41.

Muraleedharan.R

Former Member
0 Kudos

Hi,

Yes, I need a similar one for the cost also as i mentioned earlier.