Dear PS friends,

As all PS Reports in CJE0 are in controlling area currency, if we want to have these reports in other currency then how we will go.If any one has gone through such problem , pl let us know the way.

Regards,

AS

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I haven't tried it but below should be the process to report in diferrent currencies

Check if you have the All Currencies Indicator in the Controlling Area.

Also check the customising node CJEC (Currency Translation) and OB08 (Maintain Currency Exchange Rates)

In the reports choose from the menu Settings -> Currency to report in diferrent currencies.

Regards