on 01-12-2008 7:55 PM
i want to know user exit to map production planner in r3 to mrp controller in apo
Hi,
You can achive this using user exit while CIFFing the material/Product and map the appropriate fields
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes you can map your MRP controller from R3 to Production planner in APO.
YOu have to use following exit in ERP as well in APO side respectively
EXIT_SAPLCMAT_001 - Core Interface to APO: Enhancements to Material (ERP Side).
APOEXIT_/SAPAPO/SAPLCIF_PROD_001 - Inbound Processing: Products (APO Side).
Thanks,
Ravi
Did you try EXIT_/SAPAPO/SAPLCIF_PROD_001 in APO ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.