on 01-12-2008 7:19 AM
Hi ,
Can we close any project without carring out settlement ? If yes what will be the corresponding effects ?
Rgds.
ssrasam@gmail.com
Set the indicators to either 'Can be Settled' or 'Not for Settlement' in the Settlement Profile and use this profile. Projects/WBS's are only temporary cost capturing objects.
If you don't wish to allocate the costs to any receiver you don't settle it.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the reports which are based on project information data base (ex., Struture,hierarchy report) this wouldn't have any effect.
In Cost element and line item reports this would show the actuals (Debits). Had you done settlement, based on the config settings the you will see Credit on the settlement cost element or the original cost element.
Sorry I don't have any document on this.
Regards
Sreenivas
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.