on 01-11-2008 4:47 PM
Hi All,
Iam new to SCM and in the process of learning it. Iam trying to work with the realignment transaction /sapapo/rlgcopy. When i try to create a table , after characteristics selection it gives error "Realignment table cannot be activated". How do i proceed from there. Please help.
It would be helpful if somebody could send a link that explains realignment steps in detail. I tried help.sap.com , but could not understand clearly. Kindly help
Hi, there could be two reasons.
1. Authorization Issue
2. You have not created the CVC's in the planning area.
and planning area is not activated.
Only once the time series is generated will the realignment step get activated.
this problem is often faced in test systems
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi...
As mentioned earliar reply...
Hope you are having Authorization of realianment transaction...
Transaction
/SAPAPO/RLGCOPY - Data Realignment
Check that you have selected Realianment button
entered the planning object structure name
You have created table/change table
selected char to be ralianed
and then maintained entries
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Looks like an authorization problem. As soon as you get the message try transaction /oSU53 to see which object you dont have authorization for.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.