Budget exceeded

Former Member
0 Kudos

Dear Friends:

Have anyone knows PS, how to calculate budget balance?

ex : Totoal budget 1000.

2 activities and release to PR already.

ACT1(PR1) : 500. ACT2(PR2) : 400.

Budget balance = 1000 - 500 - 400 = 100.

Then transfer 100 to another WBS and set deletion flag at ACT2.

Budget balance = 1000 - 500 - 400 - 100 + 400 = 400. right?

Now I need undo deletion flag ACT2. But system will show message "Budget exceeded 400". Why? My budget balance is 400, why system show this message. I think that is bug right? Would you help me?

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi guys. Thanks a lot for your answers. But my problem still exist , I will send OSS message to SAP, if I have answered, I will tell you.

Former Member
0 Kudos

Hi,

Try tcode CJEN, CJBW and CJBN. Run it in background and make sure no posting to project (after office hours)

Enjoy PS-IM.

Former Member
0 Kudos

Hi,

Further to my earlier posting: Please run the program: RKANBU01 to resolve this problem

Muraleedharan.R

Former Member
0 Kudos

Hi Jenifer,

If your problem is not yet solved, try the following.

If you want to delete the PR, you can do so without setting the deletion flag. By doing so, the commitment also gets reduced. Try this and let me know.

regards

Pratap

Former Member
0 Kudos

Hi,

I guess this problem is on account of setting deletion flag on ACT2 before deleting the corresponding PR. Hence though deletion flag was set, commitment of 400 still remained.

Muraleedharan.R