cProjects- Customizing New Status in "Change Status"

Former Member
0 Kudos

I need to customize new status in "Change Status" drop down of cProjects tool. Now the status available are "Created, Released, Locked etc" as we all know. But i need to customize my own status for "Projects Phases and Tasks" I create. Can i do that. Please help me on the same. It is urgent.

Edited by: Visvesh Ramanathan on Jan 10, 2008 4:00 PM

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Vishvesh,

You can do the same via transaction BS02 ( Create/Change status profile). Once done, you can create your own user defined statuses for the status profile, and assign them the authorization keys.

Kindly let me know if you needed any more help.

Regards,

Vivek Pandey

Former Member
0 Kudos

Thanks a lot for the info. I have one more doubt on the same.

The status getting populated in "Change Status" drop down is through customization in SPRO?. I dont think it is been customized and also they dont maintain a standard table for this. They have used a domain "DPR_PROC_STATUS" for those standard status.

Can you please suggest on the same. Can we add more status there in the domain, will it have some impact.

Former Member
0 Kudos

Hi

As Vivek already explained, you can have user status in bs02

now here you can maintain the status as one maintains in R/3 or ECC

create an auth Key in BS52 for status which needs approval

maintain the same auth key in bs02 against status

what you have to do is create a role using pfcg and assign that key in that role

assign the role to user which ll approve the status to next status.

Select object type which will give you the applicability of status profile.

e.g the status profile is to be used for project / task / checklist etc etc...

The user statusses are visible once you select the status in 3rd tab of project

Niranjan

Award points if useful

Former Member
0 Kudos

Hi,

I created user statuse through BS02. I am now able to change them in cProject

In which tables are the links between objects and statuses written (let's say for phases)?

In which BW extractor can I find them?

Thanks

former_member201206
Active Contributor
0 Kudos

Hi Visvesh,

The system status of cProject can not be enhanced. But in the Tab 'Status' of the project, you can assign a status profile to the involved project. In the customizing, you find the item 'Create/Change Status Profile for User Status' under 'Basic Settings' of cProject.

Kind regards,

Zhenbo