on 01-09-2008 6:28 AM
Hi SAP gurus
Can u tell me the configuration for Forward Scheduling and Backward Scheduling.CAN U TELL step by step
not Def/. , Only configuration that how to do
Hi,
A routing can be scheduled using the following scheduling types:
Forward scheduling: The system schedules forward starting from the basic start date.
Backward scheduling: The system schedules backward starting from the basic finish date.
"today" scheduling: The system carries out forward scheduling using the current date as a basic start date.
no scheduling: The individual operations are not scheduled.
Based on the floats before and after production, the system calculates the scheduled start and finish and enters these dates in all operations.
The scheduling type determines which basic dates you have to enter. The following table shows the dates you must enter for the individual scheduling types as well as the dates that are then calculated using scheduling.
If you enter both basic dates, the system will make sure that the dates determined using forward or backward scheduling are within the specified period. If necessary, it will apply reduction measures.
Example Data
Material shortage date
01.08 (Friday)
Planned delivery time of the material
10 days (calendar days)
Processing time for purchasing
1 day (workdays)
Goods receipt processing time
2 days (workdays)
Opening period
10 days (workdays)
Workdays = Monday to Friday, no bank holiday
Scheduling
Material shortage date plus processing time for purchasing plan plus planned delivery time = delivery date
01.08. (Friday) plus 1 workday + 10 calendar days = 14.08. (Thursday)
Delivery date plus goods receipt processing time = availability date
14.08. (Thursday) plus 2 workdays = 18.08. (Monday)
regards,
Siddharth.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
u need to define the sales order types which will be eligle to this. as much as i understand the system does frwrd sched by default. also u need to define the lead times for the shipping points. follow the path-img-sales and dist-basic func--del and trans scheduling.
saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
forward scheduling and backward scheduling is automatically done by the system to propose requested delivery date it will done when avaliabity check carries, to carry F/B scheduling avaliabity check config settings r to bem made properly.
as per system version it will first goes to backward scheduling,
system comapares the delevary date with "pld dly time and gr processing time and transportation lead time and pur.,dept processing time" if the delivery date is in between these dates system propes the delivery date, if delivery date is in the past then the system goes for forward scheduling and then considers "pld dly time and gr processing time and pur.,dept processing time" and proposes delivery date.
Edited by: kishore gopala on Jan 9, 2008 7:52 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.